Support for farmers in Less Favoured Areas (LFAs) dominated by low productivity grassland should centre around the scientific consensus that these areas hold more potential for nature/biodiversity recovery and carbon sequestration than they do for food production. 

Looking back at the Agricultural Reform List of Measures, one of the ‘Outcomes’ persistently sought through measure implementation is, “removing drivers for biodiversity loss”.  In upland areas, in particular, sheep are the main culprit here.  Cattle may be widely debated, but sheep are indefensible; they eat everything. Therefore, actions that make the facilitation of nature recovery in severely disadvantaged areas (SDAs) more financially attractive than sheep farming are needed. 

The Reform Route Map states that the Scottish Upland Sheep Support Scheme (SUSSS) is “expected to continue in 2025 and 2026 but may be delivered using a different model from the current one”.  We would therefore suggest that this is a good area to target for change, with the new model incentivising actions that reduce grazing pressure in the uplands and permit the return of native habitats. This would also make a significant contribution towards the Scottish Government’s 30 by 30 biodiversity commitment.

Targeting SDAs by using the SUSSS criteria (farms/crofts that rely on rough grazing with 80 per cent or more of agricultural land in Payment Region 3 and less than 200 hectares of agricultural land in Payment Region 1) would take little away from food production whilst delivering significant gains for nature and climate.  

Actions that link nature recovery with livestock exclusion would be key with payments for these actions being at least equal to the SUSSS and cover lost revenue from no longer having lambs to sell.1

According to the latest figures, only 8 per cent of LFA sheep farms are profitable without support, and 28 per cent of them are still not profitable even with support.  Can there really be any valid objections then if we continue to support these farmers, at even higher rates, but with a change of activity?

It is great that the Scottish Government’s List of Measures already contains the framework to implement these changes. Under “Uncultivated Permanent Habitats”, which lists a wide range of habitats, there is a Package to “Restore and Manage Existing Nature Rich Habitats”.   We are suggesting a broadening of some of the measures listed under this package.  For example, rather than “seasonally excluding livestock” we propose funding the year-round exclusion of livestock for the duration of the 5-year plan with sheep farmers and crofters being incentivised to adopt habitat restoration as a permanent alternative by reapplying to the plan every 5 years. Data suggests that key plant species will take 10–20 years to recover in blanket bog and up to 60 years in high-altitude grasslands so viewing these actions as long term is essential for maximum biodiversity and carbon benefits.

Recommended stocking densities in uncultivated permanent habitats are already very low (the SUSSS limits payments to 1 ewe hogg per 4 ha), and in certain areas such as peatland and wetland the risks of damage (to habitats and livestock) are so high, particularly if the intensive supervision required is not provided, that livestock, especially sheep, do not belong in these areas.  Wild deer, as constant rangers, are better managers of these areas which should ideally be fenced from livestock.  We are glad to see new Cross Compliance conditions in the reform route map that prohibit “activities that cause damage to the vegetation cover exposing the soil” in wetland and peatland areas. Grazing and poaching by livestock, along with muirburn, are such activities.  

The benefits of removing or reducing livestock go beyond biodiversity restoration and the protection of sensitive areas to encompass many of the other outcomes sought through agricultural reform including improved water and air quality, less soil compaction, reduced flood risk, increase in soil carbon, fewer greenhouse gas emissions, and a better environment to support a diversity of plants and wildlife. The above blog gives useful tips on how to know if livestock removal has been successful. 

Secondly, also under the same Package (Restore and Manage Existing Nature Rich Habitats), we are proposing broadening the measure of “Small-Scale Tree and Shrub Planting” to include other habitat recovery actions such as restoring peatland by blocking artificial drainage channels, creating bunds to rewet and promote peat growth, and revegetation by planting and transplanting sphagnum moss along with heather and cotton grass to stabilise the soil and aid in peat accumulation, to give a couple of examples. Any capital costs associated with habitat restoration should be fully covered by the Scottish Government.

The habitat recovery actions would be determined by a Biodiversity Audit (BA) which must be a prerequisite for eligibility and fully funded by the Scottish Government. Along with a Carbon Audit (CA), also fully funded, the BA would outline the habitat recovery actions needed and provide essential guidance. Carrying out a BA and CA at the beginning and the end of a five-year plan period would provide a standardised way to measure gains.  

It is essential that BAs be carried out by external ecological auditors rather than the farmers/crofters themselves.  Looking at the BA that Nature Scot has been trialling, it is too complex (32 habitat and feature types, 10 scorecards), too subjective, and too time-consuming to appeal to busy land managers. The Scottish Government should contract directly with biodiversity auditors to provide these services free of charge to farmers, with the latter being paid a onetime nominal sum to arrange the service at both the start and end of the five-year plan.

The table below lists the actions mentioned with suggested payments.

Package: Create, Restore, and Manage Habitats for Biodiversity and Carbon Sequestration.

ACTIONELIGIBILITYDURATIONPAYMENTACTION’S AIM
RMH1
Arrange a free pre- and post- Biodiversity Audit on Payment Region 3 land to include mitigation plans and implementation support
Business reliant on rough grazing. 80% or more of agricultural land in Payment Region 3 and less than 200 ha of agricultural land in Payment Region 1Once at the beginning and at the end of the 5-yr period£100 to the farmer/crofter for arranging the free auditTo assess the qualitative and quantitative condition of the holding’s biodiversity at the start and end of the 5-year period
RMH2
Arrange a free pre- and post- Carbon Audit on Payment Region 3 land to include mitigation plans and implementation support

As above

As above
£100 to the farmer/crofter for arranging the free auditTo quantify and assess the greenhouse gases associated with the holding’s activities at the start and end of the 5-year period
RMH3
Following the guidance of the RMH1 audit, create, restore, and manage native habitats
Must have completed RMH1 and RMH2 and also carry out RMH45 years£588/ha/yr*
(in addition to grant funding for capital costs)
To create, restore, and manage habitats for biodiversity and carbon sequestration
RMH4
Year-round exclusion of livestock for the duration of the period
Must be conducted in conjunction with RMH1, 2, & 35 years£82/ha/yr**To allow for the creation, restoration, and management of native habitats for biodiversity and carbon sequestration 

* This payment amount is based upon DEFRA’s expanded SFI offer for 2024, SCR1 “Create scrub and open habitat mosaics” (£588/ha/yr). Land managers are allowed to include water bodies (less than 4m wide) and unsurfaced roads/tracks/paths which would typically be ineligible2 for BPS payments, which is a good additional incentive.  

There are many additional payments you could consider including here, or indeed, break the payment down into different types of restoration such as:

It is definitely worth browsing through all the actions in DEFRA’s technical annex as they cover the spectrum of habitats with numerous actions under each.

** The recommendation for carrying out SCR1 above, formerly WD8, is to remove livestock for which a supplement (WD9 – £74/ha) is paid.  The payment amount we are recommending is slightly higher than this and based upon the following calculation:

2022 SUSSS payout £61.25/ewe hogg based on 1,134 farmers/crofters claiming, 115,886 sheep. This amount should be divided by 4 as the upper limit of the SUSSS is 1 ewe hogg per 4 ha: £15.31/ha

Plus revenue lost from future lamb sales per ewe hogg assuming a 200% lambing rate, which is highly unlikely in the uplands but would make sheep removal an attractive option, (£132 per finished lamb based upon 2023 prices, 2 lambs/4 ha = £264 divided by 4 ): £66/ha 

So, sheep exclusion supplement for farms and crofts that “rely on rough grazing with 80 per cent or more of [their] agricultural land in Payment Region 3 and less than 200 hectares of agricultural land in Payment Region 1” (SUSSS criteria) rounded up = £82/ha/yr

Footnotes:
  1. Farmers and crofters in these areas would still be eligible to claim the Less Favoured Area Support Scheme (LFASS) which, for more disadvantaged land (grazing categories A and B) in very fragile island areas, is as high as £71.35/ha/yr.  Moving forward though, the necessity of having a grazing category in order to be eligible for the LFASS must be removed.
  1. On the topic of ineligible non-agricultural land, watercourses, dense vegetative cover such as impenetrable gorse, scrub, and trees must be removed from the list if we wish to encourage diverse farmland habitats for nature recovery and carbon sequestration. The GRH1 (“Management of rough grazing for birds” £121/ha) even permits the inclusion of areas of bracken.